Question: Consider the following 2-stage process. G1TP4 represent 7 resources (workers or machines). The numbers shown beside the resource names are processing times in minutes per

Consider the following 2-stage process. G1TP4 represent 7 resources (workers or machines). The numbers shown beside the resource names are processing times in minutes per unit, Answer tho following questions. Keep two decimal ploces when necessary. 7. Use the artival schedule in part c. Suppose jobs finished at G1 will go to P1, jobs finished at G2 will go to P2, jobs finished at G3 will go to P3. The flow time is minutes. Hint: How many jobs arrive at G1, G2, and G3, respectively in thour? The fow time should be the woighted average of the time spent in the process by these jobs You can type your solution procedure in the textbox below
Step by Step Solution
There are 3 Steps involved in it