Question: Consider the following 3 projects which all have the same risk (and therefore the same expect return): Par value = $1000 A) Project #1 with
Consider the following 3 projects which all have the same risk (and therefore the same expect return): Par value = $1000
A) Project #1 with the following Cash Flows:
Cash Flow at Time 0 = -2,000
Cash Flow at Time 1= 1500
Cash Flow at Time 2 = 500
Cash Flow at time 3 = 500
B) Project #2 with the following Cash Flows:
Cash Flow at Time 0 = -2,000
Cash Flow at Time 1 = 900
Cash Flow at Time 2 = 900
Cash Flow at Time 3 = 900
C) Project #3 with the following Cash Flows:
Cash Flow at Time 0 = -2,000
Cash Flow at Time 1 = 400
Cash Flow at Time 2 = 400
Cash Flow at Time 3 = 2,000
Assume that you only have $1,000 to invest. How would you invest your money? Assume a discount rate of 5%.
Please show work without using Excel