Question: Consider the following: Activity a m b Predecessor A 3 6 8 --- B 2 4 4 --- C 1 2 3 --- D 6

Consider the following:

Activity a m b Predecessor
A 3 6 8 ---
B 2 4 4 ---
C 1 2 3 ---
D 6 7 8 C
E 2 4 6 B,D
F 6 10 14 A,E
G 1 2 4 A,E
H 3 6 9 F
I 10 11 12 G
J 14 16 20 C
K 2 8 10 H,I

What is the total project completion time, assuming that we are using the 3-time estimate for activity durations. Columns "a", "m" and "b" represent the optimistic, most likely and pessimistic estimates?