Question: Consider the following: Activity a m b Predecessor A 3 6 8 --- B 2 4 4 --- C 1 2 3 --- D 6
Consider the following:
| Activity | a | m | b | Predecessor |
| A | 3 | 6 | 8 | --- |
| B | 2 | 4 | 4 | --- |
| C | 1 | 2 | 3 | --- |
| D | 6 | 7 | 8 | C |
| E | 2 | 4 | 6 | B,D |
| F | 6 | 10 | 14 | A,E |
| G | 1 | 2 | 4 | A,E |
| H | 3 | 6 | 9 | F |
| I | 10 | 11 | 12 | G |
| J | 14 | 16 | 20 | C |
| K | 2 | 8 | 10 | H,I |
What is the total project completion time, assuming that we are using the 3-time estimate for activity durations. Columns "a", "m" and "b" represent the optimistic, most likely and pessimistic estimates?