Question: Consider the following activity description with associated cost data shown in Table 1. The cost data represents the total cost and should be considered linear
Consider the following activity description with associated cost data shown in Table 1. The cost data represents the total cost and should be considered linear with time.
Table 1: Crash Cost Table
| Activity | Immediate Predecessor | Normal Duration (days) | Normal Cost ($) | Crash Duration (days) | Crash Cost ($) |
| A | --- | 5 | 50 | 3 | 150 |
| B | --- | 4 | 40 | 2 | 200 |
| C | B | 7 | 70 | 5 | 250 |
| D | A, C | 2 | 20 | 1 | 50 |
| E | A, C | 5 | 125 | 1 | 525 |
| F | B | 10 | 80 | 7 | 290 |
| G | D | 7 | 50 | 3 | 250 |
| H | E, F | 6 | 60 | 3 | 180 |
Reduce the project duration to minimum duration and calculate the cost.