Question: Consider the following: Activity Normal time (weeks) Crash time (weeks) Crash Cost per week Predecessor A 6 5 100 --- B 8 6 50 ---
Consider the following:
| Activity | Normal time (weeks) | Crash time (weeks) | Crash Cost per week | Predecessor |
| A | 6 | 5 | 100 | --- |
| B | 8 | 6 | 50 | --- |
| C | 4 | 3 | 100 | --- |
| D | 5 | 3 | 150 | A |
| E | 8 | 5 | 200 | C |
Calculate the minimum cost of crashing by 2 weeks.