Question: Consider the following: Activity Normal time (weeks) Crash time (weeks) Crash Cost per week Predecessor A 6 5 100 --- B 8 6 50 ---

Consider the following:

Activity Normal time (weeks) Crash time (weeks) Crash Cost per week Predecessor
A 6 5 100 ---
B 8 6 50 ---
C 4 3 100 ---
D 5 3 150 A
E 8 5 200 C

Calculate the minimum cost of crashing by 2 weeks.