Question: Problem 12 Assigned Media Question Help The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three


Problem 12 Assigned Media Question Help The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Activity Normal Time (weeks) Crash Time (weeks) 7 Cost to Crash ($ per week) 250 200 250 250 Immediate Predecessor(s) None None 8 11 10 5 3 A 4 2 I W T T 0 0 0 ) A B 1 1 2 2 5 3 200 200 C D D, E F 4 3 2 2 G Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole rs.) Activity Time according to schedule (weeks) Activity Time according to schedule (weeks) A 0 - IOT NON 7 50 40 8 5 5. B 460 280 20 50 5 5 70 140 P You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the anter must rent other space at a neart church at additional cost. Time and cost data for your project are contained in the table below. Your interest is in minimizing the cost of the project to the community Center Activity Normal Time Normal Cost (5) Crash Time (days) Immediate Crash Cost (5) (day) START 0 0 0 0 0 170 START B 2 250 START C 70 2 B D AC E AC F 80 B 180 G D H EF FINISH 0 GH Using the normal time for each activity, what is the earliest date you can complete the project? The corresponding project duration using the normal times is 22 days. (Enter your response as an integer.) b. Suppose the variable overhead costs me $30 per day for your project. Also, suppose that the center must pay 570 per day for a temporary room on day 16 or beyond. Find the minimum-cost project schedule Fil (. Fill in the table below to show the proper schedule time for each activity after crashing) for completing the project at minimum cost. (Enter your responses as integers) Time Activity Time (days) Activity (days) E 7 3 F 5 D H 3 c Determine the total cost for this project's schedule Total cost $ 1540 (Enter your response as an integer) The table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $12,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 14. Activity Predecessor(s) Immediate A D E F G B DE E Normal Time Crash Time Normal Cost Crash Cost (weeks) (weeks) (5) (5) 7.000 10,000 3 3 3,000 3,000 5 3 12,000 40,000 2 1 12.000 28,000 1 1 8.000 8,000 5 4 5,000 3 2 9,000 15,000 13,000 a. What is the shortest time duration for this project regardless of cost? ? The shortest project duration regardless of cost is weeks. (Enter your response as a whole number.) Problem 12 Assigned Media Question Help The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Activity Normal Time (weeks) 8 11 5 4 1 2 5 4 2 B D E F G H Crash Time Cost to Crash (weeks) ($ per week) 7 250 10 200 3 250 2 250 1 Immediate Predecessor(s) None None A A 2 2 3 3 3 2 200 200 C,D D, E F Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Activity Time according to Time according to Activity schedule (weeks) schedule (weeks) F G H B D E 1