Question: Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely

Consider the following Activity-On-Node (AON)
Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively. 4-5-6 2-3-4 B D 4-5-6 3-4-5 F A 5-6-7 3-4-5 C E Refer to the figure. What deadline should be set to ensure a 99% probability that the project will be completed within the deadline date? O 19.45 days O 19 days O 18 days 20.56 days 18.54 days