Question: Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely

Consider the following Activity-On-Node (AON)

Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively. What is the expected completion time of activity A? 4-5-6 2-3-4 B D 4-5-6 3-4-5 F A 5-6-7 3-4-5 E Click here to view a Word version of the project. 3 days 2 days 5 days 4 days