Question: Consider the following data. Draw activity on arc (AOA) network diagram. Find out critical path, expected duration, slack, total and independent floats. What is the
Consider the following data. Draw activity on arc (AOA) network diagram. Find out critical path, expected duration, slack, total and independent floats. What is the probability that it would be completed in
a. 11 weeks and
b. 16 weeks?
| Activity | Predecessor activity | Optimistic | Most likely | Pessimistic |
| A | -- | 2 | 3 | 10 |
| B | -- | 2 | 3 | 4 |
| C | A | 1 | 2 | 3 |
| D | A | 4 | 6 | 14 |
| E | B | 4 | 5 | 12 |
| F | C | 3 | 4 | 5 |
| G | D,E | 1 | 1 | 7 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts