Question: Consider the following data. Draw activity on arc (AOA) network diagram. Find out critical path, expected duration, slack, total and independent floats. What is the

Consider the following data. Draw activity on arc (AOA) network diagram. Find out critical path, expected duration, slack, total and independent floats. What is the probability that it would be completed in

a. 11 weeks and

b. 16 weeks?

Activity Predecessor activity Optimistic Most likely Pessimistic
A -- 2 3 10
B -- 2 3 4
C A 1 2 3
D A 4 6 14
E B 4 5 12
F C 3 4 5
G D,E 1 1 7