Question: Consider the following data for a project never before attempted by your company: Activity A Expected Time te (weeks) 5 Immediate Predecessor(s) B 2 3

Consider the following data for a project never

Consider the following data for a project never before attempted by your company: Activity A Expected Time te (weeks) 5 Immediate Predecessor(s) B 2 3 D 5 B E 3 C D F D a. Draw the network diagram for this project. b. Identify the critical path and estimate the project's duration. Calculate the slack for each activity. C