Consider the following data for a project to install a new server at the Northland Pines High
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider the following data for a project to install a new server at the Northland Pines High School:
Activity | Activity Time (days) | Immediate Predecessor(s) |
A | 1 | − |
B | 4 | A |
C | 5 | A |
D | 4 | B |
E | 1 | B |
F | 5 | B, C |
G | 3 | D, E |
H | 4 | F |
I | 5 | F |
J | 7 | G, H, I |
a. Choose the correct network diagram below.
b. Calculate the critical path for this project.
The critical path is______ and the project duration is_____.