Question: Consider the following data for a project to setup equipment at a new facility: Activity Intermediate Normal predecessor time 6 A B. 3 1 D

Consider the following data for a project toConsider the following data for a project to

Consider the following data for a project to setup equipment at a new facility: Activity Intermediate Normal predecessor time 6 A B. 3 1 D A A B B,C DE 3 E 4 F. 2 What is the critical path? ABCD ABDF ABEF ACEF Question 4 Consider the following data for a project to setup equipment at a new facility: Activity Intermediate predecessor Normal time A 6 B A 3 C A 1 D B 3 E B,C 4 F D,E 2 What is the earliest starting time for activity C? 07 8 o