Question: Question 3 Consider the following data for a project to setup equipment at a new facility: Activity Intermediate predecessor Normal time A 6 B A

Question 3 Consider the following data for a

Question 3 Consider the following data for a project to setup equipment at a new facility: Activity Intermediate predecessor Normal time A 6 B A 3 C A 1 D B 3 E B,C 4 F DE 2 What is the normal length of the project? O 18 O 14 15 O 16