Question: Consider the following data for questions 1 through 5 : Activity Duration ( days ) Description Preceding Activity ( ies ) A 6 Create script
Consider the following data for questions through :
Activity Duration days Description Preceding Activityies
A Create script for advertisement
B Book technical crew A
C Book actors A
D Create props and costumes BC
E Book location C
F Filming and editing DE
How many paths are there through this network?
a
b
c
d
How many critical paths are there?
a
b
c
d
Which activities have slack?
aA
bB
cE
dF
What is the slack for activity B
a
b
c
d
What is the expected duration of this project?
a
b
c
d
Which of the following statements about a networks critical paths is always true?
aThe critical paths is the path that passes through the most activities
bThe critical paths is the path with longest total time duration
cThe critical paths is the path that passes through the most slack activities
dThe critical paths is the path that gets us through the network fastest.
In these network diagrams, slack is best described a measurement of what?
aThe difference between an activitys normal cost and its crash cost
bThe difference between an activitys early start and early finish times
cThe difference between the duration of two precedent activities
dThe difference between an activitys early start and late start times
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock