Question: Consider the following data for questions 1 through 5 : Activity Duration ( days ) Description Preceding Activity ( ies ) A 6 Create script

Consider the following data for questions 1 through 5:
Activity Duration (days) Description Preceding Activity(ies)
A 6 Create script for advertisement -
B 4 Book technical crew A
C 4 Book actors A
D 3 Create props and costumes B,C
E 6 Book location C
F 5 Filming and editing D,E
1.How many paths are there through this network?
a)1
b)2
c)3
d)4
2.How many critical paths are there?
a)0
b)1
c)2
d)3
3.Which activities have slack?
a)A
b)B
c)E
d)F
4.What is the slack for activity B?
a)0
b)1
c)2
d)3
5.What is the expected duration of this project?
a)19
b)20
c)21
d)22
6.Which of the following statements about a networks critical path(s) is always true?
a)The critical path(s) is the path that passes through the most activities
b)The critical path(s) is the path with longest total time duration
c)The critical path(s) is the path that passes through the most slack activities
d)The critical path(s) is the path that gets us through the network fastest.
7.In these network diagrams, slack is best described a measurement of what?
a)The difference between an activitys normal cost and its crash cost
b)The difference between an activitys early start and early finish times
c)The difference between the duration of two precedent activities
d)The difference between an activitys early start and late start times

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!