Question: How many critical paths are there? 0 1 2 3 Below are the project steps for the creation of a television advertisement for Foolio, which

How many critical paths are there?
0
1
2
3
Below are the project steps for the creation of a television advertisement for Foolio, which is a new energy drink that the musician Coolio has created. Consider the following data for questions 1 through 5: Activity Duration (days) Preceding Activity(ies) | 6 B 5 A ( 1 3 Description Create script for advertisement Book technical crew Book actors Create props and costumes Book location Filming and editing A D 6 |B,C E 4 Ic F 7 D, EStep by Step Solution