Consider the following data (money $ and days). a. Draw the activity network of the project. b.
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider the following data (money $ and days).
a. Draw the activity network of the project.
b. Crash the activities step by step until all paths are critical.
Activity | Normal Time | Normal cost | Crash time | Crash time |
1-2 | 20 | 600 | 17 | 720 |
1-3 | 25 | 200 | 25 | 200 |
2-3 | 10 | 300 | 8 | 440 |
2-4 | 12 | 400 | 6 | 700 |
3-4 | 5 | 300 | 2 | 420 |
4-5 | 10 | 300 | 5 | 600 |
4-6 | 5 | 600 | 3 | 900 |
5-7 | 10 | 500 | 5 | 800 |
6-7 | 8 | 400 | 3 | 700 |