Question: Consider the following G703 Continuation Sheet for payment application 1 of a concrete foundation project: A B C D E F G H I J

Consider the following G703 Continuation Sheet for payment application 1 of a concrete foundation project:

A B C D E F G H I J
ITEM DESCRIPTION OF WORK SCHEDULED WORK COMPLETED MATERIALS TOTAL % BALANCE RETAINAGE
NO. VALUE FROM PREVIOUS THIS PERIOD PRESENTLY COMPLETED (G C) TO FINISH (IF VARIABLE
APPLICATION STORED AND STORED (C - G) RATE)
(D + E) (NOT IN TO DATE
D OR E) (D+E+F)
01000 General Conditions $65,000.00 $0.00 $26,000.00 $0.00
02000 Site Work and Excavation $180,000.00 $0.00 $90,000.00 $0.00
03000 Concrete $215,000.00 $0.00 $64,500.00 $0.00
Grand Totals

Given the information provided above and assuming a retention rate of 10%, complete columns G, H, I, J and the Grand Totals portion of the G703. Based on your calculations, what should the total amount listed on line item 8: Current Payment Due on the G702 Payment Application be for this project?

  • A. $280,415
  • B. $460,000
  • C. $118,935
  • D. $162,450

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!