Question: Consider the following information about a small project: Use the table below: Find a cost-effective way to reduce the completion time by 3 days. What
Consider the following information about a small project:
Use the table below:
Find a cost-effective way to reduce the completion time by 3 days.
What is the critical path by forward and backward paths? ABDG
For the tasks that are not on the critical path, task F has the longest slack.
Following the previous question, the task with the longest slack has a slack of 5 days.
The duration of the project is 25 days.
1.
Step 1: Accelerate task(s) ____ day(s)
2.
Step 2: Accelerate task(s) ____ day(s)
3.
Step 3: Accelerate task(s) ____ day(s)
| Task | Duration (days) | Immediate Predecessors | Shortest Time Possible | Acceleration Cost per day |
| A | 5 | None | 4 | $6,500 |
| B | 10 | A | 9 | $5,000 |
| C | 8 | A | 7 | $7,000 |
| D | 6 | B | 3 | $6,000 |
| E | 7 | C | 6 | $6,000 |
| F | 3 | C | 2 | $7,000 |
| G | 4 | D,E,F |