Question: 1.What is the critical path by forward and backward paths? (Do not leave space in your answers. For example, if your answer is A to

 1.What is the critical path by forward and backward paths? (Do

1.What is the critical path by forward and backward paths? (Do not leave space in your answers. For example, if your answer is A to C to E and to G, put down ACEG in the blank.)

2.The duration of the project is ____ days.

3.For the tasks that are not on the critical path, task ____ has the longest slack.

4.Following the previous question, the task with the longest slack has a slack of ____ days.

5.Find the cost-effective way to reduce the completion time by 3 days. For example, if your answer is to accelerate task A by 1 day, put down A by 1 in the blank. When you need to accelerate multiple tasks at the same time, please identify them in a single step. For example, if your answer is to accelerate B and C both by 1 day, put down BC by 1 in the blank.

6.Step 1: Accelerate task(s) ____ day(s)

7.Step 2: Accelerate task(s) ____ day(s

8.Step 3: Accelerate task(s) ____ day(s)

Consider the following information about a small project: Task Duration (days) Immediate Predecessors Shortest Time Possible Acceleration Cost per day 5 None 4 $6,500 B 10 9 $5,000 8 7 $7,000 D 6 B 3 $6,000 E 7 6 $6,000 F 3 C 2 $7,000 4 DEF Consider the following information about a small project: Task Duration (days) Immediate Predecessors Shortest Time Possible Acceleration Cost per day 5 None 4 $6,500 B 10 9 $5,000 8 7 $7,000 D 6 B 3 $6,000 E 7 6 $6,000 F 3 C 2 $7,000 4 DEF

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!