Question: Consider the following information for a project as given in the image and answer the questions that fiollows Activity Immediate Predecessor Time (Days) A 2
Consider the following information for a project as given in the image and answer the questions that fiollows

Activity Immediate Predecessor Time (Days) A 2 B UT C D 10 A, D F C O G E, F