Question: Use the data in the activity table to answer the questions below: ACTIVITY Immediate Predecessor Normal Duration (wks) Minimum Duration (wks) Crash Costs ($/wk) A

Use the data in the activity table to answer the questions below:

ACTIVITY

Immediate Predecessor

Normal

Duration (wks)

Minimum

Duration (wks)

Crash Costs

($/wk)

A

---

5

5

---

B

---

4

2

100

C

A, B

5

3

200

D

C

4

4

---

E

C

1

1

300

F

C

1

1

---

G

D

3

2

200

H

E

2

1

300

I

F

1

1

---

J

H, I

3

1

100

What is the slack time for Activity I and the early start for Activity H?

Group of answer choices

2 weeks, 11 weeks

1 week, 11 weeks

3 weeks, 10 weeks

2 weeks, 12 weeks

None of the above

Flag question: Question 11

Question 113.33 pts

Given the project activity information below, what is the total crash cost if the project manager would like to shorten the entire project by three weeks? The activity times shown below are in weeks.

Activity Predecessors Normal Time Minimum Time Crash Cost/Week
A --- 8 7 $1500
B A 5 3 $200
C A 4 2 $300
D A 3 3 ---
E B, C, D 3 3 ---
F E 3 2 $250

Group of answer choices

$300

$500

$750

$800

$950

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!