Question: Consider the following information: P V = $ 3 0 0 , 0 0 0 , E V = $ 2 5 0 , 0
Consider the following information: $$$ and BAC$ Use the schedule how project is performing
Project is behind schedule and over budget.
Can't be determined with given information
Proect is behind schedule and under budget.
Proect is on time, but over budget