Question: Consider the following make - to - stock process. Here is the process flow diagram of the process: The task times are as follows: b

Consider the following make-to-stock
process.
Here is the process flow diagram of the
process:
The task times are as follows:
b. Currently, the demand rate is 10 units
per hour. Is the process supply- or
demand-constrained? Calculate cycle
time.
cycle time is 4 minutes. Process is demand-
constrained.
cycle time is 6 minutes. Process is demand
and supply-constrained.
cycle time is 6 minutes. Process is demand-
constrained.
cycle time is 4 minutes. Process is supply-
constrained.
c. The manager of the process wants to
increase profits (i.e., revenues minus
costs). Say whether this is a good idea:
investing in Marketing to increase demand
Hire new employee to increase Process
Capacity
 Consider the following make-to-stock process. Here is the process flow diagram

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!