Question: Consider the following MRP lot-sizing problem for 6 weeks net requirements, when cost per item is $15 and order or set up cost is $55
Consider the following MRP lot-sizing problem for 6 weeks net requirements, when cost per item is $15 and order or set up cost is $55 and inventory carrying cost per week is $0.1
Weekly Net Requirements:
| 1 | 2 | 3 | 4 | 5 | 6 |
| 50 | 65 | 30 | 45 | 70 | 55 |
-
Calculate the total cost by running least total cost for MRP schedule for all 6 weeks.
-
How much is the economic order quantity for 6 weeks?
-
Calculate the total cost by running least unit cost for an MRP schedule for all 6 weeks.