Question: Delta engineering is using MRP for their production Consider the following MRP lot - sizing problem, the net requirements are shown for eight scheduling weeks

Delta engineering is using MRP for their production Consider the following MRP lot-sizing problem, the net requirements are shown for eight scheduling weeks
12
Weekly net requirements
Week
1
Requirement 50
2
60
3
70
60
5
95
75
7
60
55
The other information are as follows
Cost per item
10 $
Order or setup cost
47 S
0.5% of the item cost
Inventory carrying
cost/week
4
The company is in dilemma between adopting lot-for-lot and EOQ strategy Calculate the total cost and decide which strategy will be suitable to minimize overall costs

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!