Question: Consider the following network. Activity L has an activity time of 4 and immediately precedes activities M, P, and T. The latest start times for

Consider the following network. Activity L has an activity time of 4 and immediately precedes activities M, P, and T. The latest start times for activities M, P, and T are 22, 19, and 27, respectively. The latest finish times for activities M, P, and T are 29, 27, and 33, respectively. What is the latest start time for activity L?

A.

37

B.

15

C.

22

D.

13

E.

33

Consider the following network diagram. Activities L, M, and P are immediate predecessors for activity T, which has an activity time of 7. The early start times for activities L, M, and P are 22, 17, and 27, respectively. The early finish times for activities L, M, and P are 35, 27, and 33, respectively. What is the early finish time for activity T?

A.

24

B.

42

C.

27

D.

17

E.

40

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!