Question: Consider the following network diagram. Each arrow represents a task in the project and the duration of the task appears on top of the arrow.
Consider the following network diagram. Each arrow represents a task in the project and the duration of the task appears on top of the arrow. We note each activity by its start and ending node. for example, activity 1-3 has a duration of 8 days.
1. What is the duration of this project?
A. 13 B. 19 C. 15 D. 20 E. 52
What is the earliest start time for activity 4-7?
A. 5 B. 4 C. 0 D. 10
5 3 6 8 7 2 4 9 1) 7 6 3 6 2 5Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts