Question: Consider the following network for a 10-day course in project management: x Start >B O E Use the following table to determine which activities should

Consider the following network for a 10-day

Consider the following network for a 10-day course in project management: x Start >B O E Use the following table to determine which activities should be crashed to meet the project deadline of 10 days with a minimum cost. Activity Crash time Crashed Cost Normal Time Normal Cost (days) (days) A 4 $800 7 $500 B 2 $350 3 $200 4 $900 6 $500 D 1 $500 3 $200 E 1 $550 2 $300 Which activities should be crashed? What is the final cost of the project