Question: Consider the following network for conducting a 2 week ( 1 0 working days ) computer training class: Schematic illustration of a network for conducting

Consider the following network for conducting a 2week (10 working days) computer training class:
Schematic illustration of a network for conducting a 2-week (10working days) computer training class.
Construct a schedule showing:
ESs for all activities
LSs for all activities
Slacks for all activities
Critical path
Given the following
Activity Crash Time (days) Crashed Cost (total) Normal Time (days) Normal Cost
A: Obtain instructor 4 $8007 $500
B: Locate a room 23503200
C: Check costs 49006500
D: Room open? 15003200
E: Schedule class 15502300
$3100
Find the crash cost per day.
Which activities should be crashed to meet a project deadline of 10 days with a minimum cost? Assume partial crashing.
Find the new cost.
Is partial crashing an appropriate assumption in this kind of project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!