Question: Consider the following network for conducting a two week (10 working days) computer training class: (a) Construct a schedule showing: ESs for all activities LSs
Consider the following network for conducting a two week (10 working days) computer training class:
-1.png)
(a) Construct a schedule showing:
ESs for all activities
LSs for all activities
Slacks for all activities
Critical path
(b) Given the following.
-2.png)
1. Find the crash cost per day.
2. Which activities should be crashed to meet a project deadline of 10 days with a minimum cost?
Assume partial crashing.
3. Find the new cost.
4. Is partial crashing an appropriate assumption in this kind ofproject?
2 4 5 2 6 0 Crash Crashed Normal Timc Cost Tim Normal (days) (total) (days Cost Activity A: Obtain $800 7 $50 instructor B: Locate a room 2 C: Check costs D: Room open? 1 E: Schedule class 1 350 3 900 6 500 3 550 2 500 200 300 $3100
Step by Step Solution
3.35 Rating (161 Votes )
There are 3 Steps involved in it
Activity Crash Days Normal Crash Crash Day A 3 50000 30000 10000 B ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
84-B-M-L-P-M (511).docx
120 KBs Word File
