Question: Consider the following: --- Normal Activity Predecessor time A 4 B 2 3 D 1 A E 4 B F 7 G 2 DE If

Consider the following: --- Normal Activity
Consider the following: --- Normal Activity Predecessor time A 4 B 2 3 D 1 A E 4 B F 7 G 2 DE If the duration of activity F is reduced by 2 days, the duration of the project can be reduced by _____ days. (Fill a number in the blank.)