Question: Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the costs include both direct and indirect costs.
Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the costs include both direct and indirect costs. Immediate Normal Crash Normal Crash Activity Predecessor Time Time Cost Cost None 3 2 $200 $400 B 4 3 $300 A 1 1 $200 $200 D B and 3 2 $500 $550 E D 1 $500 $900 What are the total time of this project and total normal cost? $600 Total time is 9 days, total cost is $1700 Total time is 10 days, total cost is $1750 Total time is 11 days. total cost is $1600 Total time is 13 days, total cost is 51200 Total time is 12 days total cost is $1700