Question: Consider the following precedence chart: ACTIVITY PRECEDING OPTIMISTIC MOST PESSIMISTIC ACTIVITIES TIME (days) LIKELY TIME (days) ITIME days) 5 10 15 B 10 12 14

Consider the following precedence chart: ACTIVITY
Consider the following precedence chart: ACTIVITY PRECEDING OPTIMISTIC MOST PESSIMISTIC ACTIVITIES TIME (days) LIKELY TIME (days) ITIME days) 5 10 15 B 10 12 14 IC 10 10 B,C 2 14 16 E A 14 18 12 F IA 4 18 12 G DE 10 12 14 IF 8 12 G 2 4 10 4 The path duration for BDGJ is 32 34 30 28