Question: Consider the following process with three activities. One worker performs each activity, and the activity time of each stage is given as below. Q5. What

Consider the following process with three activities. One worker performs each activity, and the activity time of each stage is given as below.

Q5. What is the capacity of the process in units per hour?

Group of answer choices

6 [units/hour]

4 [units/hour]

3 [units/hour]

2 [units/hour]

0.5 [units/hour]

Q6. If the demand is 10 units per hour, what is the utilization of worker 3?

Group of answer choices

66.67%

333%

33.33%

50%

75%