Question: Consider the following processes along with their arrival time and burst time in milli seconds (ms) and perform the following. Draw the Gantt chart
Consider the following processes along with their arrival time and burst time in milli seconds (ms) and perform the following. Draw the Gantt chart Calculate Waiting Time of each process [1 Mark] Calculate Turn Around Time of each Process [1 mark] Calculate Average waiting Time and Average Turn Around Time [1 Mark] Using FCFS Scheduling for the following processes. Process Arrival Time R1 R2 R3 R4 (ms) 3 4 0 6 [2 marks] Burst Time (ms) 9 4 3 LO 5