Question: Consider the following project activities. Activity Duration ( days ) Predecessor A 5 - - B 8 A C 7 A D 6 A E

Consider the following project activities.
Activity Duration (days) Predecessor
A 5--
B 8 A
C 7 A
D 6 A
E 9 B, C, D
F 10 B, C, D
G 5 E, F
Find out the critical path.
Question 29 options:
A-B-E-G
A-B-F-G
A-D-E-G
A-C-F-G
A-D-F-G