Question: Consider the following project activities Activity Name Immediate Predecessor (list number/ name, separated by ,) Normal Time 1 6 2 2 3 1 3 4

Consider the following project activities

Activity Name

Immediate Predecessor (list number/ name, separated by ,)

Normal Time

1

6
2 2
3 1 3
4 2 2
5 3 4
6 4 1
7 5,6 1
8 7 6
9 8 3
10 8 1
11 9,10 1

Fill the following table:

Activity Name On Critical Path Activity Time

Earliest

Start

Earliest

Finish
Latest Start Latest Finish

Slack

(LS-ES)
1 6
2 2
3 3
4 2
5 4
6 1
7 1
8 6
9 3
10 1
11 1
Project Completion Time = Weeks
Number of Critical Path(s)=

Note : On critical path column the answer ( Yes or No ).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!