Question: Consider the following project activities Activity Name Immediate Predecessor (list number/ name, separated by ,) Normal Time 1 6 2 2 3 1 3 4
Consider the following project activities
| Activity Name |
| Normal Time | |
| 1 | 6 | ||
| 2 | 2 | ||
| 3 | 1 | 3 | |
| 4 | 2 | 2 | |
| 5 | 3 | 4 | |
| 6 | 4 | 1 | |
| 7 | 5,6 | 1 | |
| 8 | 7 | 6 | |
| 9 | 8 | 3 | |
| 10 | 8 | 1 | |
| 11 | 9,10 | 1 |
Fill the following table:
| Activity Name | On Critical Path | Activity Time | Earliest Start | Earliest Finish | Latest Start | Latest Finish | Slack (LS-ES) |
| 1 | 6 | ||||||
| 2 | 2 | ||||||
| 3 | 3 | ||||||
| 4 | 2 | ||||||
| 5 | 4 | ||||||
| 6 | 1 | ||||||
| 7 | 1 | ||||||
| 8 | 6 | ||||||
| 9 | 3 | ||||||
| 10 | 1 | ||||||
| 11 | 1 | ||||||
| Project Completion Time = | Weeks | ||||||
| Number of Critical Path(s)= |
Note : On critical path column the answer ( Yes or No ).
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock