Question: Question One Consider the following project activities: Activity Name Immediate Predecessor (list number/ name, separated by ,) Normal Time A 6 B A 2 C

Question One

Consider the following project activities:

Activity Name

Immediate Predecessor (list number/ name, separated by ,)

Normal Time

A

6

B

A

2

C

A

4

D

B, C

3

E

D

1

F

D

7

G

E

4

H

F, G

2

I

F

6

J

I

1

K

H, J

5

Fill the following table:

Activity Name

Activity Time

Earliest

Start

Earliest

Finish

Latest Start

Latest Finish

Slack

(LS-ES)

A

6

B

2

C

4

D

3

E

1

F

7

G

4

H

2

I

6

J

1

K

5

Project Completion Time =

Days

The Critical Path is=

uestion Two

Assume that ABC Company has invested a budget of 36 million riyals for XY project and planned to complete in 12 months. Lets also assume that the company planned to spend the budget equally in each month. However, when the first two months has passed, the project manager has found out that the total of two million riyals spent.

Based on the above scenario, answer the following:

Suppose RP=0.25

a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

b) How much will it actually cost the company to complete this project, and how long will it really take to complete it based on the performance to date?

c) What do o you think of the project performance? over/under the budget? behind /ahead the schedule? Justify your answer.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!