Question: a) What is the project completion time? A. 12 days B. 14 days C. 16 days D. 20 days E. None of these b) What

a) What is the project completion time?
A. 12 days
B. 14 days
C. 16 days
D. 20 days
E. None of these
b) What is the critical path?
A. CFH
B. CFG
C. BFG
D. ADEG
E. None of these
c) What is the variance of the critical path?
A. 4.32
B. 1.0
C. 3.333
D. 2.778
E. None of these
a Bragg's Bakery is building a new automated bakery in downtown Omaha. Here are the activities that need to be completed to get the new bakery build and the equipment installed. The network for this projected is also provided. Variance Activity Predecessor Expected b time A 2 4 6 B 5 8 11 7 9 17 D A 1 2 3 E B 2 4 12 F 4 4 4 G D 1 1 1 H E,F,G 2 2 2 I+ A project has the following activities, along with their estimate for completion. In order to solve this problem you should: Calculate the expected time and variance for each activity Draw the critical path diagram. Show the early start, the early finish times, the late start, and the late finish times Then determine the following answers to these questions
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
