Question: Consider the following project. Activity Predecessor Duration (days) A B D E F G H 1 J B B C AD E E F.1 3

Consider the following project. Activity
Consider the following project. Activity Predecessor Duration (days) A B D E F G H 1 J B B C AD E E F.1 3 3 6 S 7 2 9 Resores equited Plumbers Labor 2 3 1 1 3 3 4 1 3 3 1 2 2 2 4 6 Assume eleven plumbers and nine labors are available for the project. Prepare an activity schedule which satisfies the resources constraints. Priority criteria is earliest late start, then the minimum total slack, then the longer activity duration, and finally the maximum resource demand. Act. Time ES EF IS LF TS A 4 0 B 3 D 8 E 7 F 2 G 9 H 5 I 4 J 4