Question: Consider the following project data. Work Package BAC BCWS BCWP ACWP LRE WP X 2 4 , 0 0 0 2 , 2 0 0

Consider the following project data.
Work Package
BAC
BCWS
BCWP
ACWP
LRE
WP X
24,000
2,200
3,100
7,200
36,320
BAC is Budgeted Cost At Completion; BCWS is Budgeted Cost of Work Scheduled; BCWP is Budgeted Cost of Work Performed; ACWP is Actual Cost of Work Performed; LRE is Latest Revised Estimate.
All values are in GB Pounds
What is a three-point estimate for the project?
1.
24,400; 52,759; 57,318
2.
24,400; 47,148; 54,226;
3.
53,285; 24,400; 55,336
4.
24,400; 53,485; 55,336;
5.
24,400; 41,462; 55,814