Question: Question: Perform Earned Value analysis for the following project. Physical % completion and actual cost information is provided to you by crew supervisors based on

Question: Perform Earned Value analysis for theQuestion: Perform Earned Value analysis for the

Question: Perform Earned Value analysis for the following project. Physical % completion and actual cost information is provided to you by crew supervisors based on actual field progress. Status date is at the end of the Third months. Answer questions in the Blackboard Quiz. BCWS: Budget Cost Work Scheduled ($ value work should have completed by the status date) BCWP: Budget Cost Work Performed = Physical % completion x Baseline cost ($ value work actually completed) ACWP: Actual Cost Work Performed: This is a user input of $ actually spend BAC: Budget at Completion EAC (Estimated cost At Completion) = BAC/CPI (of the overall project) SV=BCWP-BCWS SPI=BCWP/BCWS CV=BCWP-ACWP CPI=BCWP/ACWP Physical % completio Task Duration Baseline cost Actual cost Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 n Project 5 mon A 1 mon After 3 months 100% 100% 50% $100 $200 B 1 mon $115 $200 $60 C 1 mon $60 D 1 mon 100% $80 $80 E 1 mon 100% $40 $40 F 1 mon 50% $75 $150 $300 G 1 mon 100% $300 H 1 mon 75% $100 $75 I 1 mon 0% $50 $0 J mon 0% $400 $0 TYANAT YSIS EV ANALYSIS Physical % completio Task Duration Planned % complete Baseline cost Actual cost BCWS BCWP ACWP SV SPI CV CPI n Project 5 mon After 3 mon A 1 mon 100% $100 $115 B 1 mon 100% $200 $200 1 mon 50% $60 $60 D 1 mon 100% $80 $80 E 1 mon 100% $40 $40 F 1 mon $150 $75 50% 100% 1 mon $300 $300 H 1 mon $100 $75 I 1 mon 75% 0% 0% $0 $50 $400 J 1 mon TOTAL Total % complete of the project=BCWP/BAC= Estimate at Complete (EAC)=BAC/CPI=

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!