Question: Consider the following project: Immediate Predecessor Activity Early start late start Duration (Days) A 0 0 3 6 B A 3 9 7 13 A

Consider the following project: Immediate

Consider the following project: Immediate Predecessor Activity Early start late start Duration (Days) A 0 0 3 6 B A 3 9 7 13 A B 7 D A 3 3 15 2 9 E CD . 5 10 E 10 14.5 3 F 10 a) Draw the network diagram of the project. b) Calculate the project completion time c) Demonstrate ways of speeding up the schedule and duration of the project