Question: Consider the following project in TABLE Q1: 1. Complete all the missed values in TABLE Q1. [5 marks] 2. Develop the network diagram using AON

Consider the following project in TABLE Q1: 1. Complete all the missed values in TABLE Q1. [5 marks] 2. Develop the network diagram using AON method and select the critical path(s) in this project. [5 marks] 3. Identify one non-critical activity in the network and explain the meaning of the floats. [5 marks] TABLE Q1: Activities list of the project Activity Duration START FINISH Preceded by ES LS EF LF Free Float FF. Total Float TE. 2 B A 4 6 A D 3 E 12 B, C D F 6 G 18 0 E, D G H 3