Question: Question 1 Consider the following project information: Table A. Activity Duration in Weeks Predecessor Total Float Resource Hours Needed/Week Total Resources Required A 3 -
Question 1
Consider the following project information:
Table A.
| Activity | Duration in Weeks | Predecessor | Total Float | Resource Hours Needed/Week | Total Resources Required |
| A | 3 | - | 6 | 18 | |
| B | 5 | A | 2 | 4 | 20 |
| C | 7 | A | 4 | 28 | |
| D | 3 | B, C | 6 | 18 | |
| E | 5 | B | 4 | 2 | 10 |
| F | 4 | D | 4 | 16 | |
| G | 2 | C | 5 | 3 | 6 |
| H | 5 | E, F, G | 6 | 30 | |
| Total | 146 | ||||
Table B.
| Activity | Duration | ES | EF | LS | LF | Float |
| A | 3 | 0 | 5 | 0 | 5 | |
| B | 5 | 5 | 12 | 5 | 12 | |
| C | 7 | 12 | 21 | 12 | 21 | |
| D | 3 | 12 | 17 | 16 | 21 | |
| E | 5 | 21 | 28 | 21 | 28 | |
| F | 4 | 17 | 23 | 22 | 28 | |
| G | 2 | 21 | 25 | 24 | 28 | |
| H | 5 | 28 | 35 | 28 | 35 |
3/-
SULIT
SULIT
(BFT 526)
- 3 -
a. Draw out the critical path in the project using AON.
(5 Marks)
b. Float data is missing from the two of the tables. Complete the float data after you have created your network diagram.
(5 Marks)
c. Calculate the total resources required for this project.
(5 Marks)
d. Consider that the maximum resource hours available per week are 15, determine which weeks are overcommitted.
(5 Marks)
please answer urgently