Question: Question 1 Consider the following project information: Table A. Activity Duration in Weeks Predecessor Total Float Resource Hours Needed/Week Total Resources Required A 3 -

Question 1

Consider the following project information:

Table A.

Activity

Duration in Weeks

Predecessor

Total Float

Resource Hours Needed/Week

Total Resources Required

A

3

-

6

18

B

5

A

2

4

20

C

7

A

4

28

D

3

B, C

6

18

E

5

B

4

2

10

F

4

D

4

16

G

2

C

5

3

6

H

5

E, F, G

6

30

Total

146

Table B.

Activity

Duration

ES

EF

LS

LF

Float

A

3

0

5

0

5

B

5

5

12

5

12

C

7

12

21

12

21

D

3

12

17

16

21

E

5

21

28

21

28

F

4

17

23

22

28

G

2

21

25

24

28

H

5

28

35

28

35

3/-

SULIT

SULIT

(BFT 526)

- 3 -

a. Draw out the critical path in the project using AON.

(5 Marks)

b. Float data is missing from the two of the tables. Complete the float data after you have created your network diagram.

(5 Marks)

c. Calculate the total resources required for this project.

(5 Marks)

d. Consider that the maximum resource hours available per week are 15, determine which weeks are overcommitted.

(5 Marks)

please answer urgently

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!