Question: Consider the following project management problem. (Noteshaper Scenario #27) Task Immediate Predecessor(s) Duration (days) A None 2 B A 4 C A, B 4 D

  1. Consider the following project management problem. (Noteshaper Scenario #27)
Task Immediate Predecessor(s) Duration (days)
A None 2
B A 4
C A, B 4
D A, B 3
E B 4
F D 2

a. Draw the Network diagram and include the Early Starts (ES), Early Finishes (EF), Late Starts (LS), and Late Finishes (LF)

b. What is the expected completion time of this project?

c. What is the critical path through this project?

d. How much slack is in Activity C? What does this mean?

e. How much slack is in Activity E?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!