Question: Consider the following project management problem. (Noteshaper Scenario #27) Task Immediate Predecessor(s) Duration (days) A None 2 B A 4 C A, B 4 D
- Consider the following project management problem. (Noteshaper Scenario #27)
| Task | Immediate Predecessor(s) | Duration (days) |
| A | None | 2 |
| B | A | 4 |
| C | A, B | 4 |
| D | A, B | 3 |
| E | B | 4 |
| F | D | 2 |
a. Draw the Network diagram and include the Early Starts (ES), Early Finishes (EF), Late Starts (LS), and Late Finishes (LF)
b. What is the expected completion time of this project?
c. What is the critical path through this project?
d. How much slack is in Activity C? What does this mean?
e. How much slack is in Activity E?