Question: Consider the following project management problem: Task Immediate Predecessor(s) Duration (Days) A none 1 B none 3 C A 6 D A 3 E B,
Consider the following project management problem:
Task Immediate Predecessor(s) Duration (Days)
A none 1
B none 3
C A 6
D A 3
E B, D 4
F C, E 1
a. What is the expected completion time of this project?
b. What is critical path through this project?