Question: Consider the following project network and cost / time information. This project has a $ 1 0 0 / day indirect cost: Activity Precedence Normal

Consider the following project network and cost/time information. This project has a $100/day indirect cost:
Activity Precedence Normal Time Crash Time Normal Cost Crash Cost
A -545070
B A 427080
C A 215060
D B 1 Can't be crashed 90-
E C 5250140
F D, E 31200600
What is the direct cost of completing this project using the normal times? (Enter a numerical value without $ or , or ".")
What is the total cost of completing this project using the normal times? (Enter a numerical value without $ or , or ".")
If you were asked to reduce the project completion time by one time unit, which activity would you crash?
What is the indirect cost of this project if we reduce its completion time by two days? (Enter a numerical value without $ or , or ".")
What is the total cost of this project if we reduce its completion time by two days? (Enter a numerical value without $ or , or ".")

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!