Question: Consider the following project network and cost/time information. This project has a $80/day indirect cost: Activity Precedence Normal Time Crash Time Normal Cost Crash Cost
Consider the following project network and cost/time information. This project has a $80/day indirect cost:
| Activity | Precedence | Normal Time | Crash Time | Normal Cost | Crash Cost |
|---|---|---|---|---|---|
| A | - | 5 | 4 | 50 | 70 |
| B | A | 4 | 2 | 70 | 80 |
| C | A | 5 | 2 | 50 | 140 |
| D | B | 1 | Can't be crashed | 90 | - |
| E | C | 2 | 1 | 50 | 60 |
| F | D, E | 3 | 1 | 200 | 600 |
- What is the direct cost of completing this project using the normal times? (Enter a numerical value without "$" or ",")
- What is the total cost of completing this project using the normal times? (Enter a numerical value without "$" or ",")
- If you were asked to reduce the project completion time by one time unit, which activity would you crash?
- What is the indirect cost of this project if we reduce its completion time by two days? (Enter a a numerical value without "$" or ",")
- What is the total cost of this project if we reduce its completion time by two days? (Enter a a numerical value without "$" or ",")
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock