Question: Consider the following project network and cost/time information. This project has a $80/day indirect cost: Activity Precedence Normal Time Crash Time Normal Cost Crash Cost

Consider the following project network and cost/time information. This project has a $80/day indirect cost:

Activity Precedence Normal Time Crash Time Normal Cost Crash Cost
A - 5 4 50 70
B A 4 2 70 80
C A 5 2 50 140
D B 1 Can't be crashed 90 -
E C 2 1 50 60
F D, E 3 1 200 600
  • What is the direct cost of completing this project using the normal times? (Enter a numerical value without "$" or ",")
  • What is the total cost of completing this project using the normal times? (Enter a numerical value without "$" or ",")
  • If you were asked to reduce the project completion time by one time unit, which activity would you crash?
  • What is the indirect cost of this project if we reduce its completion time by two days? (Enter a a numerical value without "$" or ",")
  • What is the total cost of this project if we reduce its completion time by two days? (Enter a a numerical value without "$" or ",")

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!