Question: Consider the following project network diagram B D 2 3 3 3 5 5 5 5 8 8 0 0 E End 3 Start A

Consider the following project network diagram B

Consider the following project network diagram B D 2 3 3 3 5 5 5 5 8 8 0 0 E End 3 Start A 3 C 1 8 8 11 11 11 11 7 0 0 0 0 0 3 3 8 4 3 0 4 A problem causes the duration of task C to change from 1 to 6. What is the new optimal finishing time for the whole project? (Hint: you need to recalculate the entire forward-path calculation in your head to get this one)